Updated April 5, 2019

Lab Science Building (SBC #166/011-11-2013)

Past two weeks:

  • Chiller Plant sewer upgrade in progress
  • Roofing has begun
  • Structural steel erection complete
  • Perimeter studs completed in area C
  • Concrete column pours started (first lift is 12’, then 8’ then 4’)
  • Fireproofing complete in all areas with finish slabs
  • Lecture Hall foundations and concrete walls complete
  • Real-time webcam at http://webcams.christmanco.com/TTU-Laboratory-Science-Building

Next two weeks:

  • Welding brick relief angles ongoing
  • Lower courses of brick veneer continues
  • Plumbing underground in progress
  • Roofing at gables of area A
  • Sheathing and sealant in area B
  • Mechanical, electrical & plumbing overhead in area A

Student Recreation Center (SBC #166/011-13-2014)

Current work:

  • Rough in of HVAC continues; building units have been placed and installed
  • Plumbing and electrical work continues
  • Building is now “dried in”, and windows have been installed in many areas.  Window installation is continuing building wide.
  • Roofing work nearing completion
  • Interior walls are now being installed
  • Masonry work continues
  • Pool infrastructure, pumps, and plumbing work is nearing completion
  • Real-time webcam at https://app.oxblue.com/open/denark/tennesseetech

Upcoming:

  • Continuation of above work
  • As interior spaces take shape, work in individual spaces will occur
  • Completion of glass work and masonry.

Roaden University Center (SBC #166/011-14-2014)

Current work:

  • Bridge and balcony open
  • Minor punch list items in progress

Upcoming:

  • Completion of work

Browning/Evins Residence Halls (SBC #166/011-18-2015)

Current work:

  • HVAC are units being installed
  • Cable TV and data lines are being installed
  • Doors are being installed
  • Concrete has been poured
  • Emergency phone is being installed
  • Ceramic tile is being installed in the new lobby
  • New cabinetry has been installed in new lobby and kitchen areas

Upcoming:

  • Ceiling tile will be installed in corridors
  • Carpet will be installed in corridors
  • Door installation will be completed
  • Electrical and HVAC work will continue
  • Restroom fixtures will be installed
  • Substantial Completion expected in June 2019

Bartoo and Kittrell Halls (SBC #166/011-05-2016A)

Past two weeks:

  • Installation of 90% of the laboratory casework in Kittrell
  • 3rd floor above ceiling electrical inspection completed in Kittrell
  • Dirt spoils from below grade waterproofing hauled off
  • Window frosting complete
  • Leaded glass replacement underway
  • Mark boards and associated frames installed in both buildings
  • Ceiling grids installed in Kittrell and 2nd and 3rd floor of Bartoo

Next two weeks:

  • 2nd floor above ceiling electrical inspection
  • Waterjet graphics in Kittrell flooring to be fabricated
  • Insulation of hydronic systems continues
  • Ceiling grid installation at Bartoo
  • Wiring of lay-in light fixtures continues in both buildings

Poultry Center Facility (SBC #166/011-01-2017)

  • Design of poultry houses been finalized
  • Design of multipurpose building being finalized, including lab space, abbatoir and processing room, and all equipment layouts

Library Brick Replacement (SBC #166/011-06-2016A)

Current work:

  • Brick work nearing completion

Upcoming:

  • Upon completion of brick work, excavation will begin to install a new foundation drain at the front of the building
  • Upon completion of foundation drain, new sod will be installed and Snelgrove Gardens will be replanted

Library Excavation Project/Testing and Archives (SBC #166/011-03-2016)

Current work:

  • Project substantially complete and in punch list stage

Upcoming:

  • Completion of punch list

University Drive Upgrade west of Willow Ave. (SBC #166/011-02-2016B)

  • In redesign
  • Anticipate bid in early summer 2019

Roof Replacement and Repairs (SBC #166/011-07-2015A)

Current work:

  • All roof work completed on Brown, Bruner, Clement, Hyder-Burks

Upcoming:

  • Masonry work on high walls on Bruner Hall will be started April 22
  • Landscaping repair work to begin week of April 8

Residence Hall Roof Replacement (SBC #166/011-02-2018)

Current work:

  • Shingle work on New Hall South almost complete
  • Cooper/Dunn is approximately 75% complete; work will continue on west side flat roof section

Upcoming:

  • Work on guttering and flat section of roof on north side of New Hall South to be completed in April

Back to Current Projects